Timescales for connection

If planning permission is not required for a generation connection :

  • Average time for connection is between 6- 9 months, if plant and equipment is to be ordered. The lead-in time for major items of plant and equipment can be up to 20 weeks.
  • Where NIE needs to install equipment on third party property, legal consent in the form of a wayleave agreement and/or easement is required from the relevant landowner. Timescales to obtain landowner approval depends on the landowner’s willingness to sign the legal documents.
  • Where a substation is required a substation lease must be obtained.

Diagram of 6-9 month applications process

 

 If planning permission is required: 

  • Planning Permission required for construction of any overhead line greater than 100m in length.
  • Turnaround time for planning permission approx 4 - 6 months.
  • Average time for connection is approx 9 to 12 months following acceptance of terms.

 

Diagram of generation time
 

Please note that these timescale are subject to NIE being able to secure legalities such as wayleaves, easements, substation leases and planning permission.